API RP 584: Integrity Operating Windows That Actually Get Acted On
API RP 584 defines integrity operating windows, the process limits set inside the safe operating envelope to keep equipment damage rates predictable. It classifies each limit as critical, standard or informational, requires both upper and lower bounds, and demands a named owner, a defined response time and an escalation path for every exceedance. The limit values come from the corrosion control document, not from API RP 584.
API RP 584 exists because most fixed equipment failures are not surprises in the metallurgy; they are process excursions nobody classified. The recommended practice supplies a structure rather than a table of numbers. Identify the credible damage mechanisms on each circuit, find the process variables that drive their rate, set limits on those variables that sit inside the safe operating envelope, classify every limit by the urgency of exceeding it, and name the person accountable for the response. Critical limits change damage rate fast enough that operations must act on shift. Standard limits accumulate damage over weeks and drive an inspection or engineering response. Informational limits exist to trend, refine and feed the next reassessment. The actual values come from the corrosion control document, the damage mechanism literature and the unit inspection history. What API RP 584 supplies is the discipline that turns those values into something an operator can act on.
Source: Sources: API RP 584 Integrity Operating Windows; API RP 970 Corrosion Control Documents; API RP 571 Damage Mechanisms Affecting Fixed Equipment in the Refining Industry; API RP 580 and API RP 581 Risk-Based Inspection; API RP 932-B (overhead and sour water systems); API RP 941 (Nelson curves for high temperature hydrogen attack); API RP 945 (amine unit corrosion); API 510, API 570 and API 653 inspection codes; OSHA 29 CFR 1910.119 Process Safety Management.
| IOW type | What an exceedance means | Expected response | Evidence that the window is real |
|---|---|---|---|
| Critical | Damage rate accelerates fast enough that continued operation can consume remaining life or challenge containment | Operator action within the shift, with documented escalation to the unit engineer and the inspection group | Control system alarm set at the limit, alarm rationalisation record, shift log entry, closure record |
| Standard | Damage accumulates over days to weeks; the circuit is not immediately at risk but the inspection plan assumption is broken | Engineering and inspection review inside an agreed period, typically days, with the corrosion rate reassessed | Trend chart with the limit drawn on it, exceedance report, revised corrosion rate in the data management system |
| Informational | A parameter has moved outside its expected band with no direct short term integrity consequence | Log and trend; feeds the periodic IOW and corrosion control document review | Laboratory trending record, periodic review minutes, revision history on the corrosion control document |
| Lower limit, any classification | A variable has fallen below the value that keeps a mechanism suppressed, for example wash water rate, velocity, inhibitor dose or margin above water dew point | The response assigned to its classification; a lower limit is not a softer limit | Both bounds present in the IOW register rather than a single maximum |
| No limit assigned | A credible damage mechanism is running with no process variable monitored against it | Gap closure action raised at the corrosion control document review | Traceability matrix linking every credible mechanism to at least one monitored variable |
What API RP 584 covers, and what it deliberately leaves out
API RP 584 addresses fixed equipment in refining, petrochemical and chemical service: piping circuits, pressure vessels, fired heaters, exchangers and the process conditions that govern how fast they degrade. Its subject is the operating envelope rather than the hardware. It sets out how an owner operator derives limits on temperature, pressure, flow, velocity, pH, chloride, ammonium bisulphide concentration, hydrogen partial pressure, water content, wash rates and injection rates, and how those limits reach the people who actually move the levers on the console.
The exclusions matter as much as the scope. API RP 584 is not a design document and establishes no allowable stresses. It does not replace the safe operating limits required under process safety management, which exist to prevent immediate loss of containment rather than to control degradation rate. It does not identify damage mechanisms, which is the work of API RP 571 and the unit corrosion control document. It does not set inspection intervals, which remain governed by API 510, API 570, API 653 and the risk based inspection assessment. And it publishes no limit values of its own.
That last exclusion is where most implementation efforts stall. Teams open the document expecting a lookup table and find a methodology instead. Every value has to be engineered for the specific circuit, its metallurgy, its service and its history; setting IOW limits is the owner's engineering decision, usually made by its corrosion and materials specialists. Atlantis NDT supplies the NDE that follows an exceedance.
Critical, standard and informational: the classification that decides response time
API RP 584 classifies limits by the urgency and consequence of exceeding them. A critical limit is one where continued operation outside the window drives damage at a rate that can consume remaining life or challenge containment within a short period, so the response belongs to the console operator on shift. A standard limit is one where damage accumulates over days or weeks, so the response is an engineering and inspection review inside an agreed period. An informational limit carries no direct short term integrity consequence but is trended because it refines the corrosion rate model that the inspection plan rests on.
The classification is about response time, not about how large or alarming the number looks. A five degree excursion on a critical high temperature limit in a sulphidation circuit outranks a wide swing on an informational laboratory parameter. Programmes that classify by apparent severity end up with critical alarms that operators learn to acknowledge and dismiss, which is materially worse than having no alarm at all, because it manufactures a record of compliance around a signal everyone ignores.
A useful test on any existing register: for every limit marked critical, can the shift team state without opening a document what they must do in the first thirty minutes? If they cannot, that limit is not critical in any operational sense, whatever the spreadsheet column says. Either the classification is wrong or the response has never been communicated, and both are findable in an audit.
Upper and lower bounds: the requirement most registers fail
API RP 584 expects limits to be bidirectional wherever the underlying mechanism is bidirectional, and a large share of the mechanisms that actually cause leaks are driven by a variable falling. Crude unit overhead systems are the classic illustration. The operative limit is not a maximum temperature but a minimum: the tower top or condenser inlet temperature must remain above the calculated water dew point by a deliberate margin, set deliberately by the owner's engineers for that circuit, or aqueous hydrochloric acid condenses and the local corrosion rate steps up by an order of magnitude.
The same logic runs across the plant. Velocity below a threshold lets solids settle and under deposit corrosion begin; velocity above a threshold in rich amine or ammonium bisulphide service produces erosion corrosion, so both bounds are real. Wash water rate, neutraliser rate and filming inhibitor dose each have a minimum below which the suppression the circuit relies on is simply absent. Sour water and hydroprocessing effluent systems carry both a concentration limit on ammonium bisulphide and a velocity limit that tightens as that concentration rises.
Reviewing an existing register purely for missing lower bounds is one of the fastest value adding exercises available on a mature unit, and it is quickest with the corrosion control document open alongside. It also tends to expose limits inherited wholesale from a sister plant with different metallurgy and a different feed, which is a separate and considerably worse problem.
Where the numbers come from: mechanism first, operating comfort never
Every defensible integrity operating window traces to a damage mechanism and a documented technical basis. Hydrogen partial pressure and temperature limits in hydroprocessing trace to the Nelson curves in API RP 941 for high temperature hydrogen attack. High temperature sulphidation limits trace to sulphidation rate data and the sulphur content of the stream. Ammonium bisulphide concentration and velocity limits trace to API RP 932-B. Amine velocity and temperature limits trace to API RP 945. Controls on polythionic acid stress corrosion cracking trace to the neutralisation practice applied during shutdown.
What a window must never trace to is operator comfort or historical operating range. A limit set at last year average plus two standard deviations describes how the unit has been run; it says nothing about the point at which the metal starts to suffer. Auditors ask for the basis, and the honest answer across a large fraction of legacy registers is that the person who set it has retired and the calculation file has been lost.
Recording the basis beside the limit is what lets the register survive people leaving. In practice the corrosion control document holds the mechanism, the circuit and the justification, while the IOW register holds the value, the classification and the owner, with a hard link between the two. When that link exists only in one engineer memory, the first significant feedstock change quietly invalidates the whole set and nobody notices.
Monitoring, alarms and the accountability chain
A limit that is not monitored is not a window, it is an opinion. API RP 584 forces owners to decide, for each limit, how the variable is measured, how often, by whom, and where the result lands. Continuously measured variables such as temperature, pressure and flow can be alarmed in the control system, and critical limits generally should be, subject to alarm rationalisation so the operator is not buried under nuisance alarms. Laboratory variables such as chloride, iron, pH and ammonium bisulphide are sampled on a set frequency and belong in a trending system with the limit drawn on the chart, not buried inside a monthly report.
The accountability chain is the part that decays first. Each limit needs a named response owner and a named technical owner, and both roles must survive a reorganisation. When an exceedance occurs, the record has to show who was notified, what decision was taken and when. In practice that record only exists reliably when it is captured in the same system that holds the thickness and inspection history, which is the argument for keeping exceedances inside an inspection data management system rather than in a mailbox.
For sites operating under process safety management, the exceedance record is also mechanical integrity evidence and is routinely requested during compliance audits. Sites holding that evidence in a controlled system rather than in personal spreadsheets find the audit dramatically shorter, which is one reason IOW tracking increasingly sits inside mechanical integrity software alongside the inspection plan it protects.
Exceedance response: what the procedure must actually say
The weakest sentence in most IOW procedures is the instruction to notify engineering. It defines no timescale, no decision and no closure test. API RP 584 expects the response to be specific: what the operator does immediately, who is informed within what period, what technical assessment is triggered, what evidence closes the exceedance, and what changes if the excursion repeats.
A workable definition for a critical limit reads roughly as follows. Return the variable inside the window or reduce rate. Log the excursion with start time, peak value and duration. Notify the unit engineer and the inspection group within the shift. The inspection engineer then assesses whether the assumed corrosion rate for the affected circuit still holds; if it does not, the next examination is advanced and the circuit corrosion rate is revised in the data management system. The exceedance closes only when that assessment is recorded, not when the variable returns to normal.
Duration and magnitude both matter and should be captured together. Ten minutes above a sulphidation limit is a different event from ten days at the same value, and the assessment that follows should be proportionate to the exposure. Registers that record only a binary breach flag destroy the information an engineer needs to make that judgement later, and they make it impossible to argue the case either way at the next reassessment.
The misreadings that produce audit findings
Four findings recur across sites. The first is conflation of integrity operating windows with safe operating limits, producing a single register in which the IOW values are simply the process safety limits, which are always looser. The result is a programme reporting full compliance while circuits corrode inside the window. The second is upper bounds only, which leaves dew point margin, minimum velocity and every suppression mechanism uncovered.
The third is orphan limits: numbers with no traceable mechanism, usually inherited from a sister site or a vendor recommendation, that nobody can justify and nobody is willing to change. The fourth, and the most consequential in practice, is exceedances that are logged but never assessed. An auditor who reads a year of exceedance records and finds no corresponding change to any corrosion rate, examination date or engineering assessment has found a programme generating paper rather than protection, and that finding is difficult to argue with.
A fifth appears less often in guidance but constantly in reality: the register that passes through a management of change untouched. A new feedstock, a revamped overhead, a different treatment chemical or a capacity increase all move the technical basis, so the management of change procedure should explicitly call for IOW review. Where it does not, the register drifts out of step with the plant one project at a time.
How IOWs interact with risk based inspection and inspection planning
API RP 584 sits inside a family of documents. API RP 571 describes what can go wrong. API RP 970 collects the credible mechanisms and their controls into a corrosion control document for each unit and circuit. API RP 584 sets the process limits that hold those controls in place. API RP 580 and API RP 581 convert the resulting confidence into inspection scope and interval, and API 510, API 570 and API 653 govern the examinations themselves. Remove the IOW layer and risk based inspection is resting on an assumption of stable operation that nobody is testing.
That linkage runs both ways, and it is where the programme earns its keep. Sustained operation inside the windows supports the corrosion rates the risk assessment used, which supports the interval that was granted. Repeated excursions do the opposite: they invalidate the assumption, and the correct response is to advance examinations rather than to argue with the number. Writing that reasoning down is what turns an inspection interval into a defensible position instead of a preference.
If your unit has a corrosion control document but no windows, or windows with no traceable basis, the gap usually closes faster with a structured review than with a rewrite from scratch. When an exceedance calls for inspection, Atlantis NDT carries out the follow-up NDE — request an inspection quote and we will scope it against the corrosion control documents you already hold.
Setting an IOW limit from operating comfort instead of the damage mechanism
The most common defect in an integrity operating window is not a missing limit — most programmes have limits — it is a limit derived from where the unit has historically operated comfortably rather than from the point at which a credible damage mechanism actually accelerates. A limit set at the edge of comfortable operating history looks defensible because the plant has run there before without incident, but it says nothing about the corrosion or cracking kinetics the window is supposed to be protecting against, and it can sit well inside the region where a mechanism is already accelerating without anyone having crossed a documented threshold.
This gap is invisible under normal operation and becomes visible only in retrospect, typically after an inspection finds damage inconsistent with the operating history the IOW register would have suggested was benign. The corrosion or cracking mechanism does not check the plant's operating comfort zone before it accelerates; it responds to temperature, velocity, chemistry and time, and an IOW limit that was never derived from those variables is a historical observation wearing the appearance of an engineering limit.
A defensible IOW register documents, for each limit, the specific damage mechanism it constrains and the technical basis — typically drawn from API RP 571 mechanism data or corrosion-rate modelling for the specific service — rather than citing historical operating range alone. An auditor testing an IOW programme asks for that derivation explicitly, and its absence is one of the more common findings in integrity operating window reviews.
What is the difference between an integrity operating window and a safe operating limit?
A safe operating limit protects against immediate loss of containment and is a process safety parameter; exceeding it can fail equipment now. An integrity operating window sits inside that envelope and protects the metal from accelerated degradation over time. The two are set by different disciplines from different inputs, and the IOW is almost always the tighter of the pair. Merging them into one register is the most common structural error in an IOW programme, and it always loosens the integrity limits.
Does API RP 584 tell me what my IOW limits should be?
No. API RP 584 is a method, not a data source. It describes how to derive, classify, communicate, monitor and revise limits, and it publishes no values of its own. The numbers come from the corrosion control document for the unit, from damage mechanism references such as API RP 571, from service specific documents including API RP 932-B, API RP 941 and API RP 945, and from the operating and inspection history of the actual equipment in front of you.
Why does API RP 584 insist on lower limits as well as upper limits?
Because several mechanisms are driven by a variable falling rather than rising. Overhead temperature dropping toward the calculated water dew point starts aqueous condensation and hydrochloric acid attack. Velocity falling below the threshold that keeps solids suspended starts under deposit corrosion. Wash water, neutraliser or filming inhibitor rates falling remove the suppression the circuit was designed around. A register carrying only maximum values is blind to an entire class of excursion.
Who owns an integrity operating window once it is set?
API RP 584 expects a named accountable owner for every limit, normally the operations supervisor or unit engineer for the response and the inspection or materials engineer for the technical basis. Ownership has to survive shift change, reorganisation and staff turnover, which is why the practice pushes limits into the control system, the shift handover and the inspection data management system instead of leaving them inside an engineering report nobody opens.
How often should integrity operating windows be reviewed?
On a defined cycle and on trigger. The cycle normally aligns with the corrosion control document and the risk based inspection reassessment. The triggers matter more: a crude slate or feedstock change, a treatment chemical change, a revamp or capacity increase, an unexplained inspection finding, a leak, and any management of change touching a monitored variable. A window never revisited after a feed change has stopped describing the unit it governs.
What does an auditor look for when testing an IOW programme?
Traceability in both directions. From every credible damage mechanism to a monitored variable carrying a limit, and from every exceedance back to a documented response with a date and a signature. Auditors also test whether critical limits are genuinely alarmed, whether operators can describe what they do when one is breached, and whether the last several exceedances produced any recorded engineering decision at all.
API RP 584 from the inspector's side: the short answer
Inspectors care about integrity operating windows (IOWs) because the inspection plan assumes the process runs inside them. Corrosion rates, intervals and the choice of NDE technique all depend on that assumption. When an IOW is exceeded, the assumption may no longer hold. The current API 510 and API 570 say exceedances should reach inspection or engineering staff so plans can be changed, and API 510 now lists IOW exceedances among the minimum contents of an inspection plan.
This section adds the inspection view to the IOW programme described above. It covers what the inspection codes now require, how an exceedance becomes a decision about the inspection plan, which NDE follows which kind of excursion, why baseline data decides whether that NDE is useful, and how the regulators see it. API RP 584 is a copyrighted recommended practice sold by API. We paraphrase it and the codes, and you should confirm details against your licensed copies. The API RP 584 information page is on api.org.
Editions: where API RP 584 stands now
Direct answer: API RP 584 was first published in 2014. The current second edition was published in December 2021. API describes it as a guide to classifying IOWs that gives a basis for improving process safety management. The second edition reportedly added an annex on barriers to successful IOW implementation (as described by Inspectioneering).
The first edition arrived at the same time as the inspection codes began to refer to IOWs directly. The API 510 tenth edition (2014) added a section on integrity operating windows that referred to RP 584. The API 570 fourth edition (2016) added a similar section. Both codes have since been revised: API 510 is in its eleventh edition (October 2022) and API 570 in its fifth edition (February 2024). The IOW material has stayed in place and grown. If your programme documents still cite the first edition of RP 584, or older code editions, update the references at the next review. Section numbers and wording have moved between editions.
What API 510 and API 570 now say about IOWs
Direct answer: API 510 (11th edition) says the owner-operator should run a programme to create, set and monitor IOWs, with upper and lower limits where needed. Exceedances and adverse trends should be reported to inspection or engineering staff, who may change the plan. Operating staff must tell the inspector about operation outside IOWs. Recent operating history, including IOW exceedances, is an input to inspection scheduling.
Read together, the current API 510 provisions give IOWs five roles in the inspection programme:
- An owner-operator programme. The owner should implement and maintain a programme for creating, establishing and monitoring IOWs. The code explains why. Inspection plans and intervals have historically been based on corrosion rates measured under past operating conditions. Without IOWs and process control, there is often no warning that conditions have changed in a way that undermines the current plan.
- Scope of parameters. IOWs should cover physical and chemical process parameters that could affect integrity. Examples include temperature, pressure, fluid velocity, pH, flow rates, chemical or water injection rates, levels of corrosive constituents and chemical composition. Upper and lower limits are set as needed. Start-ups, shutdowns and significant upsets deserve particular attention.
- A reporting duty. Operating, maintenance and engineering staff must tell the inspector or engineer about operation outside defined IOWs. The same list covers MOC actions, feedstock changes, failures, unusual conditions and other matters.
- A scheduling input. When examinations are scheduled, the inspection plan must consider recent operating history, including IOW exceedances, together with damage type and rate, detection capability, code limits, MOC records and any RBI assessment.
- A plan content item. The plan should describe specific considerations arising from MOCs, IOW exceedances and other operating deviations since the prior inspection.
API 510 also links IOWs to two other owner documents. One is the corrosion control document (CCD), which an owner may develop under API RP 970 to set out credible damage mechanisms by unit. The other is pressure-equipment integrity incident investigation under API RP 585. Investigation findings may lead to updates to the inspection programme, the IOWs and the CCD. The code expects these documents to be available to the people who use them, including inspectors.
API 570 applies the same logic to piping. Its fourth edition IOW section follows the API 510 text. It also uses IOWs in systemization: one characteristic that can define a piping system is a similar or related set of IOWs. Circuits grouped this way share both damage mechanisms and the process limits that control them. When an exceedance occurs, the inspector can find the affected circuits and CMLs straight away instead of searching the whole unit. Confirm the current wording in the 2024 fifth edition.
From exceedance to inspection decision
Direct answer: When an exceedance is reported, the inspector or engineer identifies the damage mechanism the limit protects against and the circuits and equipment exposed. They then decide whether the inspection plan still holds. The options are: no change, with a recorded justification; a plan amendment, such as an earlier due date or wider coverage; targeted NDE now; or an engineering assessment that the owner commissions.
The page above sets out how operations responds. The inspection response is a separate, slower chain, and it is the one auditors test against the inspection records. A workable sequence:
- Receive the exceedance with its data. Start time, duration, peak value, the instrument or sample point and the affected circuit. A binary "limit exceeded" flag is not enough to judge exposure.
- Map it to a mechanism and to equipment. Use the CCD and the IOW register to name the mechanism, such as sulfidation, HCl dew point corrosion or ammonium bisulfide erosion-corrosion. Then list the equipment and CMLs downstream of the excursion that share that exposure.
- Judge the effect on the plan's assumptions. Could this excursion have changed the corrosion rate, started a cracking mechanism, or moved damage to locations the current CMLs do not cover?
- Decide and record. The options are no action with a justification, a plan amendment, targeted NDE, or a referral for engineering assessment. API 510 frames this as modifying existing plans or creating new ones, depending on how serious the exceedance is.
- Specify the NDE if needed. Name the technique, the locations (existing CMLs plus any new ones at the most exposed points), the extent and the timing. Do this in the plan, as API 510 expects for every examination.
- Close the loop. Enter the results against the same CMLs, recalculate the corrosion rate and remaining life where relevant, and reset the next due date.
Step 4 is where programmes lose credibility. A year of logged exceedances with no recorded inspection decision is the audit finding described above. The fix is to make the inspection decision a required field in closing an exceedance.
Which NDE follows which excursion
Direct answer: The follow-up technique depends on the mechanism. Thinning mechanisms call for thickness measurement and mapping at the most exposed locations. Cracking mechanisms call for surface or volumetric crack-detection techniques. Some high-temperature mechanisms are hard to detect early, so the inspector may lean more on engineering assessment than on NDE.
| Damage mechanism (API RP 571) | Typical IOW variables | Where to look after an excursion | Common NDE follow-up and its limits |
|---|---|---|---|
| High-temperature sulfidation | Metal or process temperature, sulfur content of the feed | Hottest sections, low-silicon carbon steel components where present, components that bypass alloy upgrades | UT thickness and mapping; PMI to confirm material where the CCD flags it. Thinning can be uneven between components in the same circuit. |
| HCl dew point corrosion (overhead systems) | Temperature margin above water dew point, chlorides, neutraliser and wash rates | First condensation points, exchanger inlets, low points | UT mapping, profile RT on small bore, ET or IRIS on exchanger tubes at outage. Attack is localized, so spot UT can miss it. |
| Ammonium bisulfide corrosion | NH4HS concentration, velocity, wash water rate and distribution | Air cooler inlets and outlets, elbows, tees and flow disturbances downstream | UT mapping and RT at turbulent points; tube inspection at outage. Damage concentrates at flow disturbances. |
| Wet H2S cracking (HIC, SOHIC, SSC) | Water presence, pH, H2S level, cyanides | Plate and welds in sour water and overhead service | WFMT for surface cracking, PAUT or specialised UT for HIC and SOHIC. Usually needs an outage for internal WFMT. |
| Amine and caustic stress corrosion cracking | Temperature, amine loading or caustic concentration, steam-out practice | Non-PWHT welds and heat-affected zones | WFMT, ACFM, PAUT on welds. Crack detection depends on surface preparation and access. |
| Chloride SCC (austenitic stainless) | Chloride level, temperature, oxygen | Stainless components, including under insulation | PT or ET for surface cracking. Branching cracks can be hard to size. |
| High-temperature hydrogen attack | Temperature, hydrogen partial pressure (API RP 941) | Carbon and C-0.5Mo steel equipment, welds and HAZ in hydrogen service | Specialised advanced UT techniques; early-stage damage is difficult to detect reliably. Owners usually rely on engineering assessment and material upgrades rather than NDE alone. |
| Erosion and erosion-corrosion | Velocity, solids content, flow regime | Elbows, reducers, downstream of control valves and injection points | UT mapping and profile RT at the outer radius and downstream locations. |
| Corrosion under insulation | Operating temperature range and cycling (not usually a process IOW, but often monitored) | Insulated carbon steel in the susceptible temperature range, penetrations and supports | Pulsed eddy current or profile RT screening, then UT or VT with insulation removed. |
The table describes common practice. It does not replace your unit's CCD or the inspector's judgement. For a fuller technique-to-mechanism comparison, see our NDE method selection by damage mechanism guide. For individual mechanisms, see the API RP 571 page, sulfidation corrosion and HTHA and API RP 941.
Baseline data: why the follow-up NDE needs a "before"
Direct answer: An exceedance raises the question of whether the corrosion rate has changed. Only repeat measurements at the same locations, with a comparable technique, can answer it. If IOW-sensitive circuits have no baseline at their most exposed points, follow-up NDE can show current thickness but not how fast it is changing.
This is the practical reason to build IOW-sensitive locations into the inspection plan before anything goes wrong. When the CCD links a circuit to an IOW, the plan should already contain CMLs at the points that would react first to an excursion. Examples are the first condensation point in an overhead, the elbow downstream of an injection, and the hottest section of a sulfidation circuit. Those CMLs need recorded readings, taken with a stated technique and reading pattern.
Several details decide whether before-and-after data can be compared:
- Location repeatability. CMLs must be marked, sketched or otherwise located so the next reading is taken at the same point. A short shift in position can look like corrosion.
- Technique consistency. Spot readings and mapping grids give different kinds of answers. Moving from spot UT to a mapping grid after an exceedance is often the right call, but record it so the first mapped result is not read as a rate.
- Temperature effects. Many follow-up readings happen on-stream at elevated temperature. High-temperature UT needs suitable probes and couplant, and the procedure should state how readings are corrected for temperature.
- Coating and surface condition. Readings through coating, or on corroded external surfaces, need a procedure that accounts for them.
Our guide to long-term and short-term corrosion rates explains why the short-term rate is the one an exceedance threatens, and why it is most sensitive to measurement scatter.
Start-ups, shutdowns and upsets
Direct answer: API 510 asks for particular attention to IOW monitoring during start-ups, shutdowns and significant upsets. These transient periods can push variables outside their windows in ways that steady-state alarms are not set up to catch. Inspectors should expect to review transient records after each one.
Some examples show why:
- Dew point excursions at start-up. Overhead systems can run below the water dew point margin while temperatures are still rising.
- Polythionic acid SCC during shutdown. Sensitized austenitic stainless steel exposed to air and moisture after sulfide scale forms can crack. Shutdown protection practices, such as those in the AMPP (formerly NACE) standard on this subject, are a form of IOW for the shutdown period.
- Hydrogen and temperature transients. Hydroprocessing start-ups and shutdowns follow defined procedures for heating, cooling and hydrogen outgassing. Departing from them can affect the equipment the HTHA and hydrogen-embrittlement limits protect.
If a shutdown precedes a turnaround, transient records from that shutdown belong in the inspection team's review before the equipment is opened. They may justify extra NDE at the exposed locations. See turnaround inspection planning.
Regulatory overlay: OSHA PSM, EPA RMP, CSB and Canada
Direct answer: OSHA PSM does not use the term "IOW". It does require process safety information that includes safe upper and lower limits and an evaluation of the consequences of deviations. Operating procedures must cover operating limits, consequences of deviation and the steps to correct or avoid a deviation. Mechanical integrity inspections must follow good engineering practice, and changes need management of change. An IOW programme is one way owners show these elements work together.
Under 29 CFR 1910.119(d)(2)(i), process technology information includes safe upper and lower limits for items such as temperatures, pressures, flows or compositions, and an evaluation of the consequences of deviations. Under (f)(1)(ii), operating procedures address operating limits, including the consequences of deviation and the steps needed to correct or avoid it. The mechanical integrity element in (j) requires inspection and testing that follows recognized and generally accepted good engineering practice, more often where operating experience shows it is needed, with documented results. Management of change under (l) covers changes to process chemicals, technology, equipment and procedures. API RP 584 and the IOW sections of API 510 and API 570 sit across all four. EPA's Risk Management Program has parallel requirements at Program 3 facilities. Our OSHA PSM 1910.119 page covers the mechanical integrity element in more depth.
The US Chemical Safety Board has published investigation reports on refinery failures involving mechanisms that IOWs are designed to manage. These include high-temperature hydrogen attack at the Tesoro Anacortes refinery (2010) and sulfidation corrosion at the Chevron Richmond refinery (2012). Both reports are public on csb.gov. They are useful reading for any team setting or reviewing limits on those mechanisms.
Canada note. ABSA's AB-506 (Alberta, Edition 4, Revision 0, issued October 2025) defines an integrity operating envelope/window in terms close to API's: limits on process variables that can affect integrity if exceeded for a predetermined time. It also lists monitoring of process variables among the possible contents of an inspection plan. Plans under an Alberta owner-user integrity management system must be approved and endorsed by an In-service Inspector. Other provinces regulate pressure equipment under their own regimes, so confirm the requirements with your provincial regulator.
How Atlantis supports IOW-driven inspection
Designing an IOW programme, setting limits and assessing their engineering basis are owner process-safety and engineering functions. Atlantis does not perform them, and does not offer RBI or fitness-for-service assessments. Atlantis performs the NDE that follows: UT thickness surveys at IOW-sensitive CMLs, corrosion mapping and PAUT where an excursion may have caused localized loss, TOFD and PAUT on welds, WFMT and ACFM where cracking is suspected, profile radiography and eddy current tube inspection. Technicians are certified under an ASNT SNT-TC-1A written practice, with ASNT Level III oversight of procedures. Your API-certified inspector specifies the scope, evaluates the results and remains inspector of record. See our inspection services and pressure vessel inspection services. Ask us about follow-up NDE after an IOW exceedance and we will return a quote.
API 584 questions inspectors ask
What is API 584?
API RP 584, Integrity Operating Windows, is API's recommended practice for setting, classifying, monitoring and responding to limits on the process variables that drive equipment damage. The current edition is the second edition, published in December 2021.
Is API RP 584 mandatory?
It is a recommended practice. API 510 and API 570 refer to it and say owners should run IOW programmes. Whether that becomes a binding requirement depends on how your company, your jurisdiction and your PSM programme adopt these documents as good engineering practice.
How does an IOW exceedance affect inspection intervals?
It can shorten them. API 510 lists recent operating history, including IOW exceedances, as a scheduling input. The inspector or engineer decides whether the plan, the due date or the NDE scope needs to change.
Does API 570 require integrity operating windows?
The fourth edition (2016) added an IOW section that refers to API RP 584 and says owners should implement IOW programmes. Check the wording in the current fifth edition (2024).
What NDE is done after an IOW exceedance?
It depends on the mechanism. Thickness surveys and mapping are used for thinning mechanisms, and WFMT, ACFM, PAUT or TOFD for cracking mechanisms. Specialised techniques, backed by engineering assessment, are used for mechanisms such as HTHA.
What is the difference between API RP 584 and API RP 970?
API RP 970 covers corrosion control documents, which set out the credible damage mechanisms for each unit. API RP 584 covers the process limits that keep those mechanisms under control. In practice the CCD gives the basis, and the IOW register holds the limits.
Need follow-up examinations at IOW-sensitive circuits? Request a baseline CML survey or ask about targeted PAUT.
Need this applied on your job?
Atlantis writes and reviews procedures to the codes you work under, and provides the inspection and the training.